FacadeCSI 04 01 00 / 04 20 00
SCOPE OF WORK

Repointing, unit replacement, and lintel work on brick, stone, and terra cotta — scoped by the joint and by the unit.

Applicable Standards

ASTM C270, ASTM C1324, ACI 530, TMS 0402, NPS Preservation Brief No. 2, BIA Technical Notes, OSHA 29 CFR 1926.1153 (silica), Secretary of Interior's Standards

Condition Survey
  • Systematic visual inspection and hammer sounding of all masonry surfaces; document delaminated and deteriorated areas.
  • Photograph all deficiencies; produce deficiency map on elevation drawings.
  • Probe all mortar joints to assess bond and depth; expose representative wall ties to check corrosion.
  • Classify deficiencies: Immediate Hazard / Critical / Moderate / Minor.
Mortar Analysis & Matching
  • Collect existing mortar samples from minimum 3 locations per facade face.
  • For historic masonry: submit samples for lab analysis per ASTM C1324.
  • Produce cured mortar color chips for Owner approval.
  • CRITICAL: replacement mortar must never exceed compressive strength of masonry units.
Mortar Type Selection
  • Type N (750 psi): above-grade exterior — most common for repointing.
  • Type S (1,800 psi): below-grade, structural CMU, foundations.
  • Type O (350 psi): historic pre-1900 brick, soft stone.
  • NHL 3.5/5: historic and landmark — no Portland cement; SHPO-grade.
  • Lime putty: pre-1900 brick; SHPO Grade A restoration.
Mortar Removal
  • Minimum removal depth: 3/4 inch from face — no feathered edges; no face-pointing.
  • Hand chisel required on all historic masonry, stone, terra cotta, and joints narrower than 3/8".
  • OSHA 1926.1153 silica: HEPA vacuum at all power tools; wet suppression; respiratory protection mandatory.
Mortar Application
  • Pre-wet joint faces to SSD condition before applying mortar.
  • Pack in maximum 3/8" lifts; allow each lift to reach thumbprint hardness.
  • Tool joints to match original profile (concave preferred; no raked joints on exterior).
  • Mist freshly tooled joints 2–3 times daily for 3 days; protect from direct sun, wind, rain, and freezing.
Explore all trades
MORE TRADES
Concrete & Structural
Concrete Repair
Cast-in-Place
Precast
CMU
ICF Walls
Foundations
Epoxy Injection
Grout Injection
Steel
Waterproofing & Joints
Coatings
Sealants
Expansion Joints
Roofing
Facade & Finishes
Facades
Masonry
Windows
Siding
Paint